How to verify an installer’s licence

Search the company’s legal name in the licence lookup run by your own state’s regulator, then check the licence class against what your state requires for photovoltaic work — a valid licence in the wrong class is the failure a lookup will not catch.

There is no national answer to what that class is. Reading the regulators’ own documents for 12 states produced five different arrangements, and in three of those states we could not establish which licence covers the work at all.

What licence does a solar installer need?

It depends on the state, and the variation is wider than the advice "use a licensed installer" implies. Reading each regulator's own classification document for 12 states turned up five distinct arrangements. A small number of states have a solar contractor licence of its own that names photovoltaic work. Several have no solar class at all and treat a photovoltaic array as ordinary electrical work. Two reach it through a building trade licence rather than an electrical one — in one of them the binding credential is a residential home builders licence, because the array is fixed to the roof. Others license nothing statewide that reaches a residential job, leaving the requirement to the city or county. And in three states we could not establish the answer from the regulator's own documents and have said so rather than guessed. So the question is not "is this company licensed?" but "is it licensed in the class my state requires for this work?"

Verified against primary sources on .

What each state requires

One row per state, with the credential to ask for and the date we last read the regulator's own document. The lookups themselves are on the Installers page.

What a residential solar installer must actually hold in each state on this site, and when each was last checked against the regulator's own document.
StateWhat the state requiresThe credential to ask forChecked
AlabamaA building trade licenceAn unlimited residential home builders licence from the Alabama HBLB
AlaskaNot established — see belowNot established — the interconnection rules are what the utility will check
ArizonaThe ordinary electrical licenceAn electrical classification (C-11, R-11 or CR-11) — the Solar Exam is for thermal work
CaliforniaA solar licence of its ownC-46 Solar Contractor
GeorgiaThe ordinary electrical licenceAn ordinary electrical or general contractor licence — Georgia runs no solar board
IndianaNot established — see belowNot established — the codes and the local authority are what bind
MaineThe ordinary electrical licenceA Maine-licensed electrician for the electrical work; racking is expressly excluded
MinnesotaA building trade licenceResidential building contractor or remodeler licence, plus a licensed electrical contractor
MissouriNothing statewide — your city decidesWhatever your city or county requires — the statewide electrical licence is optional
NebraskaNot established — see belowNot established — but a State Electrical Division inspection is mandatory before interconnection
OhioNothing statewide — your city decidesWhatever your city or county requires — Ohio licenses no residential contractors
UtahA solar licence of its ownS202 Solar Photovoltaic Contractor, plus E200 or E201 for the wiring

The five patterns, and the sharpest example of each

A solar licence of its own

Two states license solar as its own trade. Utah's S202 Solar Photovoltaic Contractor may fabricate, construct, install or replace photovoltaic modules — and the same rule expressly excludes the wiring, connections and wire methods governed by the National Electrical Code, which must be done by a general or residential electrical contractor. Utah Admin. Code R156-55a So a compliant Utah job involves two licences, and a company holding only the solar one cannot lawfully do its own interconnection. California's C-46 Solar Contractor is written the same way and carries the same kind of limit: a C-46 licensee "shall not undertake or perform building or construction trades, crafts, or skills, except when required to install a thermal or photovoltaic solar energy system." CSLB — C-46 Solar Contractor

This is the pattern where checking the class matters most, because the register will show a company with only the solar licence as validly licensed. It is.

The ordinary electrical licence

Three states have no solar class and treat the array as electrical work. Arizona is the one that catches people out: the Registrar of Contractors does run solar classifications, and they are for solar thermal — plumbing including solar, air conditioning including solar, solar plumbing liquid systems. Those are the ones requiring the Registrar's Solar Exam. Rooftop photovoltaic work runs under the ordinary electrical classifications, none of which require it. AZ ROC — License Classification Requirements A claim that Arizona photovoltaic work needs a solar exam is one of the two secondary licensing claims this site has had to correct.

Maine draws the most precise line found anywhere. Its Electricians' Examining Board rule makes a complete photovoltaic installation an electrical installation, and then carves out the other half of the job:

The mere construction or placement of a support structure intended to hold or support a photovoltaic system (including racking and mounting equipment such as frames, racks, rails, and footings) that does not itself convert solar energy into electric energy does not constitute an "electrical installation."
Me. Electricians’ Examining Board Rules, Ch. 160 — Maine Office of Professional and Occupational Regulation Statutory authority 32 M.R.S. §§ 1101, 1153, 1153-A

That single sentence explains a crew where not everyone on the roof is an electrician, and it is the clearest statement on this site of who must be licensed for which task.

A building trade licence

Two states reach solar through construction licensing rather than electrical licensing. Alabama is the surprise: its Home Builders Licensure Board was asked whether a residential home builders licence is needed to install solar panels, and answered that it is — an unlimited one. The reasoning turns on the roof. The Act reaches a residential roofer once the cost exceeds $2,500, a rooftop array is fixed to the roof, and the Board considers that the work spans more than one trade and may affect the structural integrity of the roof:

regardless of the economic threshold, it is the opinion of the Board that an unlimited license is required for the installation of solar panels upon a residence
Ala. Home Builders Licensure Board, AD OP 22-06 — Alabama Home Builders Licensure Board Reverses the practical effect of AD OP 08-049 (2008)

The Board is careful about its own reach: the opinion states that it "is not binding on a court of law" and encourages review with legal counsel. It is still the issuing body's published position, which is what a homeowner would be measured against.

Minnesota gets to a building trade licence by a different route and for a reason worth knowing: since July 1, 2023 a company contracting with a Minnesota homeowner for a rooftop system must hold a residential building contractor or remodeler licence, while the electrical work itself must be done by a licensed electrical contractor. Minnesota DLI That first licence is what gives the homeowner access to the state's Contractor Recovery Fund if the company fails mid-project — the one case on this site where the licence is directly worth money to the customer.

Nothing statewide

Two states license nothing at the state level that reaches a residential solar job. Ohio is the cleaner example and it goes further than having no solar class: the state licenses no residential contractors of any trade. Its Construction Industry Licensing Board covers five commercial trades, and residential requirements are set by municipalities. Ohio Dept. of Commerce — OCILB

Missouri has a statewide electrical contractor licence and the office that issues it answers the obvious question directly: asked whether the licence is required, it says "No. The statewide electrical contractor license is optional, not mandatory." Missouri Office of Statewide Electrical Contractors The state issues no permits and inspects no work. In both states the questions worth asking are which local licences the contractor holds and which authority will inspect the job.

Not established

In three states we could not establish which licence covers photovoltaic work, and each says so on its own page rather than being rounded to whatever its neighbours require. In one, the licensing authority's own profession list would not load and we declined to infer a negative from a page that failed to render. In another, the state's rules approach installer competence through the interconnection requirements instead of a trade licence, so what the utility will check is documented and what the state requires is not. In the third, the regulator publishes a searchable list of licence classes with no solar class among them — and naming one of the others without reading the scope-of-practice document behind it is exactly the guess that produced the two wrong licensing claims this site has already had to correct.

What to do before you sign

  1. Get the licence number in writing, held by the entity that will sign your contract. A number belonging to a subcontractor, an owner personally, or a related company is a different fact from the one you asked for.
  2. Search the legal name, not the trading name, in the regulator's own lookup. These differ more often than people expect.
  3. Check the class against the work. This is the step almost nobody takes and it is where the failures are. In a state with a dedicated solar licence, ask who is doing the electrical connections and under which licence.
  4. Ask what happens if the company fails mid-project. The answer is a recovery fund in one state on this site and nothing at all in several others.
  5. Ask who pulls the permit and who inspects. In the states with no statewide licensing this is the layer that actually governs the job, and in one state a mandatory state inspection stands between a finished array and a working net metering arrangement. Neb. Rev. Stat. § 70-2004(1)
  6. Separate the licence question from the contract question. Licensing tells you the work may lawfully be done. It tells you nothing about the production estimate, the financing, or what happens to your incentives — and in 2026 that last one is where the money is. Buy versus lease is here.

Worth knowing that some states legislated the customer's side rather than the installer's. Georgia's Solar Power Free-Market Financing Act bars your utility from demanding safety or performance standards, tests or liability insurance beyond the national codes. Georgia HB 57 (2015) Indiana wrote a customer bill of rights the attorney general enforces, including the right to be told the value of every tax credit and incentive you may receive — which is precisely what a 2026 pitch still quoting a 30% federal credit gets wrong. What actually happened federally.

What this page does not cover yet

Common questions

How do I verify a solar installer’s licence?

Search the company's legal name in the licence lookup run by your state's own regulator — the board or division that issues the licence — rather than in a marketplace directory. Then do the step most people skip: check the licence class against what your state requires for photovoltaic work. A company can hold a genuine, current licence in a class that does not cover the job, and the register will show it as valid because it is. Confirm the licence belongs to the entity signing your contract rather than to a subcontractor, and get the number in writing before you sign.

Is there a national solar installer licence?

No. Licensing is a state function and the states have not converged. Reading each regulator's own documents for the 12 states on this site turned up five different arrangements — a dedicated solar licence in some, the ordinary electrical licence in others, a building trade licence in two, nothing statewide in others, and three states where we could not establish an answer at all. Advice to "use a licensed installer" is therefore incomplete on its own: it only becomes actionable once you know which licence your state means.

Can a solar company be licensed but still not allowed to do the electrical work?

Yes, and in the states with a dedicated solar licence it is the normal case. Utah's S202 Solar Photovoltaic Contractor may install the modules and related components, but the rule expressly excludes the wiring, connections and wire methods governed by the National Electrical Code — those must be performed by a general or residential electrical contractor, whom the solar contractor may employ or subcontract. So a compliant job involves two licences. If your installer holds only the solar classification, ask who is doing the interconnection and under which licence number.

What if my state does not license solar installers at all?

Then the requirement has usually moved to your city or county rather than disappeared. Ohio licenses no residential contractors of any trade at state level — its licensing board covers five commercial trades — so residential requirements are municipal. Missouri has a statewide electrical contractor licence that its own issuing office describes as optional rather than mandatory, and the state neither issues permits nor inspects the work. In both cases the questions that matter are which local licences the contractor holds, who pulls the permit, and which authority will inspect the job.

Why does this page say the answer is unknown for some states?

Because it is, and saying so is more useful than a confident guess. In three of the 12 states here we could not establish which licence class covers photovoltaic work from the regulator's own documents — in one case the licensing authority's profession list would not load, and we declined to infer that no requirement exists from a page that failed to render. Secondary claims about solar licensing have been wrong in every state on this site that had one, including two we had to correct, so we do not name a licence class without reading the scope-of-practice document behind it. For those states, ask the regulator directly which licence covers the work being proposed.

Does a licence mean the installer is any good?

No. A licence is a floor rather than a recommendation: it generally means the holder met an experience or examination requirement, carries whatever bond or insurance the state demands, and can be complained about to a body with power to act. In one state on this site it is worth more than that, because Minnesota's residential building contractor licence gives the homeowner access to a state recovery fund if the company fails mid-project. What no register tells you is whether the workmanship will be good, whether the production estimate is honest, or whether the financing is reasonable.

Primary sources

Every one of these was opened and read on the date shown. None of it is copied from DSIRE, EnergySage, or any other aggregator.

Get told when this changes

Solar incentives in your state moved three times in the first half of 2026. We recheck every program on this site on a schedule and email you when a number, a deadline, or a rule actually changes — not on a newsletter cadence, and not when nothing has happened.